20 Dwellings for Rent and Shared Ownership with Associated External Works and Drainage

  • Detailed environmental surveys carried out to aid and guide our approach especially with regard to bats.
  • Extensive demolition of existing council depot with selective recycling of demolition arisings.
  • This site was extremely tight logistically, so we utilised ‘Just in Time’ deliveries from local builders’ merchants due to the lack of on-site storage.
  • We continually liaised with the local residents and community to ensure that they were fully aware of the site operations.
  • All deliveries were scheduled out of key commuting times both in the morning and afternoon.
  • We utilised our long-standing supply chain to resource this site to ensure a high-quality finish.
  • We instigated a detailed traffic management plan which we shared with the local community to allay fears concerning irresponsible parking and safety of children on the access roads to the site.
  • This site was completed safely, on programme, to the highest quality and within budget.